56. A supplier describes its contract as fixed price while several assumptions remain unresolved. How would you assess project exposure?

MediumPlanning & scope

Case
Show model answer

Review the actual scope, assumptions, acceptance, dependencies, change terms, and responsibilities with the commercial owner. A fixed headline price does not by itself establish who bears every possible change or delivery risk.

Clarify material uncertainties before relying on the cost and schedule forecast, using appropriate contractual advice. Keep customer-side effort and excluded work visible rather than interpreting a contract label as complete protection for the project.

What interviewers listen for

  • Review the actual terms and assumptions
  • Clarify risk ownership with commercial specialists
  • Expose excluded work and customer-side effort
A supplier describes its contract as fixed price while several assumptions remain unresolved. How would you assess project exposure — Project management intervi