57. A critical purchase is scheduled to start only when the delivery team needs the item. What is missing from the plan?
MediumPlanning & scope
Case
Show model answer
Identify the steps required before usable receipt, such as specification, approval, sourcing, contracting, production, transport, inspection, and configuration. Confirm actual lead times and responsibilities with procurement and the receiving team.
Integrate those dependencies and decision dates into the schedule, including credible uncertainty. An intended order date or supplier conversation does not prove an item is committed, available, delivered, or ready for project use.
What interviewers listen for
- Map the full path to usable receipt
- Confirm lead times and decision ownership
- Distinguish intended, committed, received, and usable states