52. What should accompany a project cost estimate so another person can evaluate it?

EasyPlanning & scope

Technical
Show model answer

Describe the scope, quantities, rates, method, data date, assumptions, exclusions, and uncertainty. Identify which figures are quoted, observed, or estimated and whether relevant procurement, transition, and operating costs are included.

Link the estimate to its underlying work and owners, retaining important versions. A detailed total without its basis makes it difficult to assess completeness, explain changes, or update the forecast when assumptions fail.

What interviewers listen for

  • Document scope, method, assumptions, and exclusions
  • Distinguish evidence from estimated inputs
  • Link costs to work and preserve versions