51. What would you inspect before trusting a schedule simulation’s promised completion confidence?
HardPlanning & scope
Technical
Show model answer
Check network logic, duration assumptions, uncertainty distributions, correlations, resource constraints, and whether important risks are represented. A sophisticated simulation can produce precise-looking percentiles from an incomplete or unrealistic underlying plan.
Compare results with relevant delivery evidence and sensitivity analysis, explaining what drives the range. Use the output as decision support with explicit limitations rather than treating a modeled confidence level as a guarantee or hiding omitted risks.
What interviewers listen for
- Validate the plan and uncertainty assumptions
- Inspect correlations and omitted risks
- Explain drivers and limits of modeled confidence