99. Describe a project practice you deliberately simplified because its administrative cost exceeded its decision value.
MediumBehavioral
Behavioral
Show model answer
Choose an actual practice and explain which decisions it was meant to support, what burden it created, and the evidence that simplification was appropriate. Identify any mandatory control that still had to be preserved.
Show the agreed change and how you checked whether useful visibility or assurance was lost. Report the actual effect rather than declaring that fewer meetings or documents necessarily made the project more effective.
What interviewers listen for
- Compare administrative effort with decision value
- Preserve applicable mandatory controls
- Check the actual effect of simplification