100. A project must close while some noncritical obligations continue. How would you make closure responsible rather than cosmetic?
HardBehavioral
Managerial
Show model answer
Identify outstanding work, residual risk, contractual duties, records, benefits, and the receiving owners and resources. Confirm which closure criteria are genuinely satisfied and which require an explicitly authorized exception or continuing arrangement.
Obtain informed ownership and required decisions, with practical access and follow-up dates. Do not keep the project artificially open for every future activity, but do not label unresolved obligations complete or transfer them to an unnamed team.
What interviewers listen for
- Separate closure criteria from continuing obligations
- Secure informed ownership and resources
- Record authorized exceptions and follow-up